METRO PHASE TO BE INVESTIGATED IN CHENNAI CENTRAL MINES

In Tamil Nadu, Metro Rail service was functioning from Chennai Washerampet to the airport, covering 23 km from the first line and 22 km to the 2nd line from Central to St Thomas Mount.

The first phase works are completed in Koyambedu-Alandur, Alandur-St Thomas mount, Airport-little mount and Nehru park-Airport Metro Rail service.

For the subway, as the first phase of the two tunnels with a length of 3 thousand 616 meters between May Day Park – Tennampet is 80% completed and the 2nd route is 72.5% completed.

Similarly, the first tunnel in the 2-meter length of 2 thousand meters is up to 33.35 per cent, and the 2nd route is 43 per cent.

The Officials from Chennai, Central Housing and Urban Development, Chennai and Durga Shankar Mishra, the new chief of Metro Rail, arrived in Chennai to inspect the ongoing Metro Rail Works in Chennai.

They went to the metro rail mines in Chennai Central. Then the authorities ordered the authorities to finish the work. During the inspection, officials from Chennai Metro Railway Pankaj Kumar Bansal were also present.